Frequently Asked Question - How would the DoWCoP be applied to a phased project where material from one phase may not be returned until a subsequent phase?

How would the DoWCoP be applied to a phased project where material from one phase may not be returned until a subsequent phase?

This would hinge on the certainty of use and the time scale involved, but does fit within the scope of the DoWCoP. The Materials Management Plan should clearly identify the phased approach.

CL:AIRE will not be responsible for any loss, however arising, from the use of, or reliance on, the information contained in the responses above, nor do they assume responsibility or liability for errors or omissions in the information provided. Readers are advised to use the information contained herein purely as a guide and to take appropriate professional advice where necessary.