Ref # | Date of Submission | Location | Quantity | Availability From - To | Material Type | Chemical Analysis Available? |
---|---|---|---|---|---|---|
D051 | Sept 2014 | Oxford | >100,000m3 | From January 2015 to December 2015 | Oxford clay | Available on request |
D050 | July 2014 | Mill Hill, North London | 25,000m3 | Immediately | Reworked London Clay | Available on request |
D049 | June 2014 | South Coventry | 300,000m3 | January 2015 | Clay and Mercia Mudstone | Available on request |
D048 | May 2014 | Harlow | 200m3 | Immediate | Sub Soil and Rocks | Available on request |
D047 | April 2014 | Bridgend | 10,000m3 | Immediate | Silty/Sandy Dredged Material | Available on request |
D046 | April 2014 | Swansea | 2,000m3 | April 2014 | Clean/inert Glacial Till Soils | Available on request |
D045 | April 2014 | Swansea | 10,000m3 | April 2014 | Clean General and Engineering Fill | Available on request |
D044 | March 2014 | Sandwell, West Midlands | 830m3 | Late April 2014 | Gravelly sand (slightly silty) | Available on request |
D043 | Feb 2014 | Sheffield | 20,000m3 | Immediate | Clayey soils - greenfield site | Available on request |
D042 | Dec 2013 | Wandsworth | 8,000m3 | April/May 2014 | Alluvium and River Terrace Gravels | Available on request |
D041 | Nov 2013 | Cambridge | 400m3 | March April 2014 | Virgin topsoil, slightly silty clay characteristics | Available on request |
D040 | Sept 2013 | Lambeth | 2,000m3 | Oct 2013 | Soils & stones | Available on request |
D039 | June 2013 | Rochdale | 8,000m3 | July 2013 | Clayey made ground | Available on request |
D038 | 04/06/2011 | High Wycombe | Between 1,000 & 250,000m3 | April 2011 onwards | Clean chalk fill | Full chemical and geotechnical analysis can be made available on request |
D037 | 05/03/2011 | Fulham | 90,000 m3 | 2013-2021. Approximately 10,000 m3 per year | 50-75% material is granular made ground, 25-50% are gravels | Majority is non-hazardous although does have some coal tars. Full analysis on request |
D034 | 07/11/2011 | Holmer, Hereford | 8,000 m3 | Immediate - July 2013 | As dug topsoil | Available on request |
D029 | 15/03/2012 | Northamptonshire | 175,000 m3 | July 2013 onwards | High-quality, cohesive virgin clay | Permeability testing and full analysis on request |
D028 | 19/03/2012 | Chatham | 20,000t | Immediate | Inert soils processed into aggregates including hydraulically bound materials | - |
D027 | 19/03/2012 | Woolwich, South London | 100,000 t | Apr-12 | Sand | - |
D026 | 22/03/2012 | North Nottinghamshire | >50,000 m3 | Oct-12 | Greenfield Topsoil | Available on request |
D021 | 24/07/2012 | Canalside in England | 35,000 t | Yearly | Wet sediment dredgings | - |
D024 | 27/07/2012 | Tankersley | 1480 m3 | Sept-12 | Topsoil/organic material | Available on request |
D023 | 27/07/2012 | Tankersley | 2000 m3 | Sept-12 | Brown slightly gravely silty clay. Firm to very stiff orange/brown/grey clay | Available on request |
D020 | 01/08/2012 | Bridgend | 8000 m3 | Immediately | Clean tested subsoil | - |
D019 | 24/08/2012 | West/Central London | 40,000 m3 | Now, for 1 year | London Clay (Brown and Blue) | Available on request |
D017 | 16/10/2012 | South Cambridge | 10,000 m3 | Immediate | Naturally occurring topsoil | - |
D011 | 29/10/2012 | Colchester | 100,000 m3 | Immediate | London Blue clay | - |
D010 | 12/01/2013 | South West London | 100,000 m3 | January 2014 - May 2014 | Mostly Made Ground, some River Terrace Gravel | Available on request |
D009 | 18/01/2013 | Wilmslow | 1,000 m3 | Immediately | Clean sandy clay | Available on request |
D008 | 01/03/2013 | West Hendon | 15,000 m3 | January to December 2013 | Subsoil class 2C | Available on request |
D007 | 18/03/2013 | Manchester | 150,000 m3 | Late 2013 | Granular subsoil and made ground | Available on request |
D006 | 03/04/2013 | Ashford | 55,000 m3 | Oct-13 | Non-haz soils | Available on request |
D005 | 10/05/2013 | Saffron Waldon | 4,000 m3 | Immediate | Gravelly clay | Available on request |
D004 | 30/05/2013 | Canning Town | 12,000 t | Immediate | Inert | Available on request |
D003 | 31/05/2013 | Solihull | 1,000 m3 | Immediate | Excated fill | Remediated - analysis |
D001 | 11/06/2013 | Mill Hill | 35,000 m3 | Jul-13 | Clean London clay | Available on request |